Main Street 2024

Good morning business owners & residents! 

 

We have made it through our first official week of work on the USH 14 project in Westby.  All tree trimming and cutting will be completed by the end of this week.  On Monday, April 1st, demolition will begin on the carwash building.  The erosion control contractor will be installing various erosion control devices along the project and saw cutters will be on site early in the week to start sawing sidewalk, driveways and streets for removals to start later in the week.  You will also notice more traffic control devices on site later next week and traffic lane widths will start to be reduced.  Please remember that while we do try to provide an accurate anticipated schedule, things can change based on a multitude of factors.  As always, we appreciate your patience and understanding throughout this project.  Enjoy the rest of your week and weekend!

 

Thanks,

CORRE Logo

Elizabeth Reis
Project Manager
1222 N Superior Avenue, Tomah, WI 54660
  507.313.8436
Teams  Teams