USH 14 City of Westby: Project Update

Residents & Business Owners,

 The update is being sent a day early, due to the significant delays to traffic that may be incurred during work the rest of the week.  The contractor is going to begin placing concrete pavement near Black River Street heading south tomorrow.  During this time, only one lane of traffic will be able to travel through portions of downtown.  USH 14 and sideroad intersections will be flagged.  Some side streets will be closed during this time, as well.  Delays may be significant and if you are able to use alternate routes, please consider doing so.  Next week, some intersections will remain closed and additional concrete work will be continuing to tie in at side streets. 

 The South Street intersection should be rocked and re-opening by the end of the workday today.  This will be your best access to the school during downtown concrete work, once reopened.   

 Removals have started from Park Street heading north.  If you are accessing properties along the closed section of HWY 14 near the roundabout, please use extreme caution.  During removals some crossings will be unavailable, and you may have to share side streets and alley access with more vehicles.

 Another reminder that the concrete may need to be sawcut during overnight or early morning hours.  We apologize for that inconvenience.

 Thank you for your patience and enjoy the rest of your week!