City of Westby Road

We are getting closer to the end of our first of two construction seasons on this project.  Mid to late next week the concrete pavement is scheduled to be placed from South Street to the south end of the project, followed by the section from Black River to the north through the roundabout.  There will again be some significant delays during the concrete placement and flaggers will be on site to control traffic along the work area.  Please be patient and consider using an alternate route during these times if you are able.  Message boards will be up to assist you during these days.

 Concrete for sidewalk, driveways and terraces areas will be poured over the next few weeks.  Please do not attempt to cross, walk, drive, bike, etc on any areas that have been freshly poured or have been coned/taped off.  Damage to these areas will require replacement and will delay the opening of those sections of the project.  Work is anticipated to continue into mid to late November/early December, weather permitting.  Again, thank you for your patience and understanding during this project.

 

Thanks,

CORRE Logo

Elizabeth Reis
Project Manager
1222 N Superior Avenue, Tomah, WI 54660
  507.313.8436
Teams  Teams